George from Tempe Az writes,
11/20/2014:

Can Termidor SC be applied more than 48 hours before a preconstruction slab is poured?

What is the recommended time frame to treat preconstruction slabs with termidor SC?

Answer:

Termidor SC needs atleast 24 hours to bond to soil before pouring a concrete slab. You should apply Termidor SC at the rate of 1 gallon per 10 square feet.  You should apply slightly more around the perimeter edges and around any plumbing pipes or expansion joints that will be in the slab.

Answer last updated on: 11/20/2014