What procedure do I use when concrete steps are in the way of drilling Termidor treatment holes?

Steps for entering house are in the way for drilling perimeter of concrete patio for Termidor. Is it okay to keep the recommended hole pattern and drill around the concrete steps. Steps protrude away from house 3 feet and this is the site of known termites.

Answer:

The steps should be drilled as well to apply the Termidor SC if possible. We recommend that you drill the holes 10-12" apart and disperse 4 gallons of finished solution every 10 lineal feet.

Answer last updated on: 05/19/2014